Boiler Repair
The first Work Weekend of the winter was held this past Saturday at Larson Welding. Jobs to be done included dome valve repair and rolling flues. Here Tom H is working on the dome valve for the new Marion/Osgood shovel boiler. Mark K, Jason O, and Jace M also worked on this project.
The totally re-built dome valve on the big boiler. Nice sandblasting job Jason!
Back inside, Don B was re-building valves that go on the big Marion / Osgood boiler.
Ryan U. ran the drill on the roller as Clayton helped moved the roller from hole to hole and lubricate the rolling tool. When that was finished, they moved the boiler outside and began beading over the smokebox end of the tubes. This is a very noisy process and that is the reason for doing it outside. Ryan and Clayton had 70 tubes done when their arms started to get tired, so many others got to take their turn and learn how to bead the tubes over. So this was also an educational process for many.
The first Work Weekend of the winter was held this past Saturday at Larson Welding. Jobs to be done included dome valve repair and rolling flues. Here Tom H is working on the dome valve for the new Marion/Osgood shovel boiler. Mark K, Jason O, and Jace M also worked on this project.
The totally re-built dome valve on the big boiler. Nice sandblasting job Jason!
Back inside, Don B was re-building valves that go on the big Marion / Osgood boiler.
Ryan U. ran the drill on the roller as Clayton helped moved the roller from hole to hole and lubricate the rolling tool. When that was finished, they moved the boiler outside and began beading over the smokebox end of the tubes. This is a very noisy process and that is the reason for doing it outside. Ryan and Clayton had 70 tubes done when their arms started to get tired, so many others got to take their turn and learn how to bead the tubes over. So this was also an educational process for many.
Actually, we had to con Josh into wearing it, and he is always such a good sport about stuff like this! That's why we like him around!
But why does the shovel need a slab, Isn't it on wheels so it will meve around?
Work continues on the boom. The areas that were filled with wood blocks are now filled with steel boxes. All the internal welding on the boom rails is completed and the side skins (the area occupied by the dipper stick) are reinstalled. The top and bottom wear plates are installed (again inside the boom rails where the dipper stick will rub). It easier to renew wear plates than to rebuild the boom. The next step is mostly cosmetic work, reinstalling the "bull gear" and the hoisting chain rollers. Painting will follow ASAP. So far, we estimate that we have used about 500 pounds of welding rods . 